Finally on 20th. December 2017, our Malacca renovation works have been completed.
It has practically took us 9 months to complete this project. Originally, it was supposed to be completed in 2 months.
The main contractor was unable to meet his dateline and the main air well gutter job was not correctly mounted.
Water flowed down the air well gutter until we have to buy a plastic sheeting to prevent water seepage.
We then organise our own Malacca gutter workers to change the gutters.
With at least 4 workers and their boss around, the job was completed in 1 day.
We also installed a new Panasonic 1 HP split aircond in the senior room as well.
A single metal bed, mattress and 2 single mattresses were bought for parents single beds.
Now, the room is livable and ready for occupancy.